Key Takeaways
- • Blue Owl, Ares, Blackstone, KKR and Apollo are positioning their alternative-asset platforms around owning AI data center infrastructure and collecting long-term contracted rent, according to Reuters.
- • Blue Owl reports more than 130 data centers operating or under construction, representing nearly 14 gigawatts of leased and owned capacity, with another 21 gigawatts in its pipeline.
- • Ares estimates AI-related capex demand at just over $5 trillion through 2030, including roughly $2 trillion for physical data center buildings and adjacent power generation and transmission.
- • Blackstone says 96% of its data center portfolio counterparties are rated investment grade, with most initial lease terms running 15 to 20 years.
- • Moody's warns that concentration, construction, residual-value and circular-financing risks are growing even as many AI infrastructure borrowers are investment grade.
Summary
Blue Owl Co-CEO Marc Lipschultz said the firm leases its infrastructure for 15 to 20 years with annual rent escalators, producing what he described as a highly predictable and growing income stream for investors. He said Blue Owl seeks to limit risks tied to short-term leases and token pricing. Blue Owl CFO Alan Kirshenbaum said the firm does not expect demand for computing power to decline and added, "We are taking Microsoft, Amazon, Meta, credit risk." Shares of alternative managers rose on the day of reporting, with Blue Owl up 6.5%, Ares Management up 2%, KKR and Blackstone each up 2.5%, and Apollo Global up 3.7%.
Ares said its data center strategy targets metropolitan areas including Tokyo, Osaka, London and Sao Paulo, pre-leasing projects to investment-grade hyperscalers under 12- to 15-year leases with no termination rights and inflation escalators. Blackstone, in a post-earnings call, said the vast majority of its data center portfolio has initial lease terms of 15 to 20 years, with 96% of counterparties rated investment grade and an average market capitalisation of $2.5 trillion. Blackstone President Jonathan Gray said, "So when we think about risk, that doesn't feel particularly risky to us."
Ares estimates AI-related capital expenditure demand at just over $5 trillion through 2030, including roughly $2 trillion for physical data center buildings and adjacent power generation and transmission infrastructure. Ares CEO Michael Arougheti said investors are becoming more discerning about counterparty risk and how to price it, and downplayed the effect of higher borrowing costs on AI capex financing, arguing the alternative would be equity funding. He said funding has shifted from equity to high-grade debt and is now flowing into leveraged finance and private credit markets.
Moody's said this week that AI and digital infrastructure are creating large, long-duration financing needs that broaden the private credit market beyond traditional direct lending. The rating agency noted that "many borrowers and counterparties are investment grade. However, concentration, construction, residual-value and circular-financing risks are growing."
Go deeper than the headline
Research every firm in this story, track the ones that matter and get the daily briefing — free for 7 days.